Drainage
Final drainage plan and report or memo showing compliance with master study is required (Section 3 of the EDS&PM).
At a minimum plan shall show:
-
Retention basins or other storage facilities and clearly indicate which areas of the project will drain to each retention basin/connected series of retention basins/storage facility.
-
Contours, bottom elevations, high water elevations, 1 foot freeboard elevations, and volume provided shall be shown for each basin.
Water
City of Goodyear is the water service provider.
If a new or relocated potable water meter is required to serve the site, a new public water easement may be required. Additional documentation for water easement will be required.
A final water design report or a memo referencing the master development study and how this site is in compliance with the master study is required with the next submittal.
- This memo/report should contain the basic items such as water demand, fire demand, and sizing of pipe diameters.
Sewer
City of Goodyear is the sewer service provider.
A final sewer design report or a memo referencing the master development study and how this site is in compliance with the master study is required.
157th Water Reclamation Facility (WRF) Service Area:
- The 157th Ave (WRF) is currently in an enhanced monitoring period as required by ADEQ and MCESD. During this period, an at-risk wavier will be required to be signed, notarized, and provided to the City prior to issuing a sewer capacity letter or signing the MCESD Approval to Construct (ATC). The at-risk wavier will be recorded on the property by the City prior to permit issuance. Once the sewer capacity letter is requested, the at-risk wavier will be provided, with accompanying documentation on planned City projects to increase capacity at the plant, and additional information on the Enhanced Monitoring.
Traffic
Traffic Impact Analysis (TIA):
Driveways: